Islamabad: Financial anomalies during fiscal year 2006-07 cost CDA kitty Rs 1bn
12-25-2008, 11:44 AM
Post: #1
Islamabad: Financial anomalies during fiscal year 2006-07 cost CDA kitty Rs 1bn
* Irregularity in IJ Principal Road construction resulted in a loss of Rs 289.6 million
* Advance payment of Rs 202.9 million by utility service providers not adjusted

By Muhammad Bilal

ISLAMABAD: The Auditor General of Pakistan (AGP) has detected over one billion rupees worth of irregularities in the Capital Development Authority (CDA) expenditures during fiscal year 2006-07. The AGP pointed out such anomalies as non-recovery of dues and wasteful expenditures in its audit report, 2006-07, placed before the National Assembly on Wednesday.

IJ Principal Road: The report highlighted a loss of Rs 289.6 million to the CDA exchequer during the IJ Principal Road construction.

It said the CDA canceled the contract for the construction of the road in question from Pirwadhai Intersection to Faizabad Interchange (Phase-II) in Islamabad and entrusted the remaining work to another contractor in November 2005 ‘at risk and cost’ of the original contractor. However, the authority failed to recover Rs 289.6 million from the original contractor, it said.

Advance payment: The report also revealed the CDA made advance payments to Islamabad Electric Supply Company (IESCO), Sui Northern Gas Pipelines Limited (SNGPL) and Pakistan Telecommunication Company Limited (PTCL) for the shifting of utility lines during 2005-06.

These utility service providers were required to submit adjustment vouchers/documents to the CDA on completion of the assigned tasks for adjustment in accounts but this didn’t happen resulting in non-adjustment of advance payment of Rs 202.9 million, it said.

The audit report pointed out non-recovery of Rs 149.3 million property tax by the CDA from the IESCO. The tax has been outstanding since 1995 against various buildings and land owned by the IESCO.

It also said the CDA failed to recover Rs 145.8 million property tax and water charges from the owners and occupants of commercial buildings. It said the amount had been awaiting recovery since 1991.

The CDA, however, managed to recover Rs 32 million outstanding dues during 2006-07 leaving behind Rs 113.8 million worth of balance, it said.

Also highlighted in the audit report was a loss of Rs 33.5 million through non-transfer of funds in profit and loss account.

According to it, the CDA Directorate of Land Rehabilitation maintained a current account in a scheduled bank for acquisition of land with an amount of Rs 1.291 billion. An amount of Rs 652.688 million was disbursed leaving unspent 49 percent of the released funds (Rs 638.386 million).

This unspent balance remained in current account for seven months during 2005-06, which was neither invested in the short-term deposit scheme nor was it transferred to profit and loss account of the authority. This non-transfer of funds in profit and loss account resulted in a loss of Rs 33.5 million to the authority.

In another case, the CDA failed to obtain performance bond valuing Rs 32.2 million from a contractor of an approved local insurance company within 20 days of the issuance of acceptance letter in 2005. A bond by unapproved insurance company was accepted. The contractor defaulted and the contract was cancelled in 2007, so the performance bond couldn’t be encashed within validity period, causing the CDA Rs 32.2 million financial loss.

The audit also revealed Rs 32.2 million worth of damage to the CDA kitty through payment of a mobilisation advance to a contractor on a conditional bank guarantee of a non-scheduled bank instead of irrevocable one in violation of terms and conditions of the original contract. Under the rules, neither a building or structure can be raised nor can an addition/alteration to it be made without the CDA’s prior approval.

In the above case, the CDA issued notices to the owners of plots including Shifa International Hospital for said violations during 2005-06 but couldn’t impose/recover penalties valuing Rs 22.2 million.

The report also showed wasteful expenditures of Rs 21.6 million in the rehabilitation of Kashmir Highway. The AGP report revealed non-recovery of Rs 20 million annual fee from cellular operators by the CDA.

http://www.dailytimes.com.pk/default.asp...008_pg11_1
Quote this message in a reply
Post Reply 


Possibly Related Threads...
Thread: Author Replies: Views: Last Post
  PDWP Approves Three Lahore Development Projects with a Total Cost of PKR 7561.473 Mil LRE-Azan 0 259 01-04-2024 01:56 PM
Last Post: LRE-Azan
  LDA's Remarkable Financial Achievement: Retrieval of PKR 700 Million in FY 2022-23 LRE-Azan 0 278 10-31-2023 05:59 PM
Last Post: LRE-Azan
  Pakistan’s economy to recover modestly to 1.9% in fiscal year 2024 LRE-Azan 0 344 09-20-2023 07:24 PM
Last Post: LRE-Azan
  Pakistan receives US$2 billion in financial support from Saudi Arabia LRE-Azan 0 655 04-08-2023 02:21 PM
Last Post: LRE-Azan
  Paved with gold: Metro bus roadwork to cost thrice as much as Kashmir Highway widenin Salman 0 4,490 03-28-2014 02:27 PM
Last Post: Salman
  Prime Minister's low-cost housing scheme: 25 percent share for non-gazetted employees Salman 0 7,049 01-02-2014 01:33 PM
Last Post: Salman
  National Housing Policy 2013 Coming Soon for low-cost houses Salman 0 7,626 11-28-2013 01:31 PM
Last Post: Salman
  Ring Road project: Two bids shortlisted for financial evaluation Salman 0 6,357 10-28-2013 03:20 PM
Last Post: Salman
  PM Nawaz visits Turkey’s low cost housing scheme Salman 0 9,217 09-19-2013 05:27 PM
Last Post: Salman
  Flawed Interchange design to cost CDA Rs700 million Salman 0 4,212 12-28-2012 03:46 PM
Last Post: Salman
  Pir Wadhai flyover cost rises Salman 0 4,395 09-04-2012 02:12 PM
Last Post: Salman
  Financial plan 2012-13: RDA proposes over Rs1b budget for development Salman 0 5,440 07-07-2012 11:52 AM
Last Post: Salman
  Development, but at what cost? Salman 0 3,535 06-05-2012 12:47 PM
Last Post: Salman
  CDA proposes Rs26b budget for next fiscal year Salman 0 3,506 05-21-2012 01:12 PM
Last Post: Salman
  Financial crunch delays Zero Point loop construction Salman 0 4,301 04-25-2012 12:42 PM
Last Post: Salman
  NHA’s liabilities in maintenance cost slashed to Rs 7.5bn Salman 0 3,718 04-24-2012 12:16 PM
Last Post: Salman
  Shaikh reviews NHA’s financial needs for 5 projects Salman 0 3,883 03-20-2012 12:26 PM
Last Post: Salman
  Construction of ‘Hathi Ghar’ at cost of Rs 20m in Safari Park Lahore_Real_Estate 0 3,866 02-27-2012 11:58 AM
Last Post: Lahore_Real_Estate
  Abu Dhabi group enters in mobile financial services Salman 0 4,450 02-11-2012 12:36 PM
Last Post: Salman
  CDA to probe Park Enclave tendering process anomalies Lahore_Real_Estate 0 3,682 02-07-2012 12:41 PM
Last Post: Lahore_Real_Estate

Forum Jump:


User(s) browsing this thread: 1 Guest(s)