Islamabad: Faisal Avenue Flyover: Opening of underpasses likely this month
09-08-2008, 07:05 AM
Post: #1
Islamabad: Faisal Avenue Flyover: Opening of underpasses likely this month
By Imran Naeem Ahmad
ISLAMABAD: Officials of the Capital Development Authority (CDA) insisted on Sunday that underpasses that form part of Faisal Avenue Flyover would be opened to traffic this month.

Although a September 15 deadline has been set for the contractor to do so, it appears unlikely that carpeting of the road will be completed by then. “There might be a delay of a few days yet the ‘barrel’ would become functional this month,” assured CDA Director General (Works) Abdul Jabbar Melano.

Several deadlines have come and gone yet work on the project that began more than a year ago has only seemed to move at a slow pace. Hiccups along the way, among them monsoon rains and escalation in cost of construction material, have hampered work. The project, being executed along the Faisal Avenue, has now become as much a thorn for the CDA as it is for the public because of its slowness.

Faisal Avenue - stretching from Zero Point to Faisal Mosque - is one of the busiest roads in town and has for long borne the bulk of Islamabad’s traffic but ever since work on the flyover began road users have been greatly disturbed.

Not willing to commit to a completion date of the entire flyover, Melano however said that he foresaw substantial completion of the project by end of this year. “By December a lot should be up with the flyover getting into quite a good shape,” he hoped.

Unplanned road projects: Few of the CDA’s road projects have gone unplanned in recent years that have not only angered the public but also embarrassed the city fathers.

In June, the CDA announced that underpasses, running underneath Nazimuddin Road, Jinnah Avenue and Fazal-e-Haq Road, would become operational in July yet pre-monsoon rains seemingly put back all those plans.

Critics point out that the contractors often used rains as a pretext for projects delayed for other reasons. They cite the example of 7th Avenue and China Chowk underpasses, which too were apparently delayed on account of monsoons.

While work on the flyover inches forward, some of the CDA’s new projects have failed to take off for one reason or the other. Zero Point Interchange project remains stuck, as are the others to expand Garden Avenue and Kashmir Highway.

Currently, Faisal Venue flyover and the Islamabad Highway are the only two projects on which work is in progress.

http://www.dailytimes.com.pk/default.asp...008_pg11_1
Quote this message in a reply
Post Reply 


Possibly Related Threads...
Thread: Author Replies: Views: Last Post
  Punjab Chief Minister Announces Anticipated Opening of LRR SL-3 by Month-End LRE-Azan 0 234 01-12-2024 02:17 PM
Last Post: LRE-Azan
  Deadline Set for the Opening of Shahdara Chowk and Ravi Bridge LRE-Azan 0 230 01-04-2024 01:58 PM
Last Post: LRE-Azan
  Rawalpindi Ring Road (RRR) Project: 12% Completion, Anticipated Opening in August LRE-Azan 0 222 01-02-2024 06:14 PM
Last Post: LRE-Azan
  LDA City is set to hand over plot possessions next month LRE-Azan 0 244 11-24-2023 04:30 PM
Last Post: LRE-Azan
  Opening of Possession in DHA Lahore Phase 9 Prism – Sectors F & G LRE-Azan 0 228 11-14-2023 02:59 PM
Last Post: LRE-Azan
  LDA Major Infrastructure Projects in Lahore to Open to Traffic This Month LRE-Azan 0 239 11-08-2023 06:52 PM
Last Post: LRE-Azan
  Interest from 21 Construction Firms for Margalla Avenue-M1 Link Project LRE-Azan 0 330 11-01-2023 06:02 PM
Last Post: LRE-Azan
  CM Punjab Visits Ring Road Southern Loop-3 Ahead of its Opening LRE-Azan 0 340 10-14-2023 03:24 PM
Last Post: LRE-Azan
  CDA Decided to Auction Commercial & Residential Plots Next Month LRE-Azan 0 356 09-30-2023 04:55 PM
Last Post: LRE-Azan
  CDA approved construction of linking road from Margalla Avenue to M1 LRE-Azan 0 409 08-18-2023 06:37 PM
Last Post: LRE-Azan
  Opening of Fuel Station in DHA Multan LRE-Azan 0 516 04-01-2023 04:43 PM
Last Post: LRE-Azan
  LDA extends tender opening date of Babu Sabu Interchange project LRE-Azan 0 702 01-26-2023 03:14 PM
Last Post: LRE-Azan
  IJP Road to open to traffic by the end of month LRE-Azan 0 676 01-26-2023 03:05 PM
Last Post: LRE-Azan
  Good news: Margalla Avenue to be Completed ‘Very Soon’ – Chairman CDA LRE-Azan 0 820 01-21-2023 01:15 PM
Last Post: LRE-Azan
  Islamabad: Work on Bhara Kahu Bypass to Start Next Month LRE-Azan 0 1,033 11-02-2021 06:34 PM
Last Post: LRE-Azan
  Grand Avenue Lahore Residential Plots For Sale 24 Sep 2016 Salman 0 6,233 09-24-2016 12:51 PM
Last Post: Salman
  Metro Bus service will start functioning by the end of the next month. Salman 0 5,117 04-30-2015 05:19 PM
Last Post: Salman
  LDA Avenue 1 Final Notice To AllotteesFor Payment of Outstanding Dues Salman 0 5,385 04-18-2015 05:02 PM
Last Post: Salman
  Allottees of LDA Avenue-I have to wait for possession Salman 0 6,602 03-31-2014 07:36 PM
Last Post: Salman
  LDA Announced To Hand Over Possession Of Plots In LDA Avenue 1 From 31th March Salman 0 14,158 03-26-2014 06:06 PM
Last Post: Salman

Forum Jump:


User(s) browsing this thread: 1 Guest(s)