Post Reply 
 
Thread Rating:
  • 0 Vote(s) - 0 Average
  • 1
  • 2
  • 3
  • 4
  • 5
Nepra allows six discos to raise power tariffs
08-06-2009, 07:11 AM
Post: #1
Nepra allows six discos to raise power tariffs
MUSHTAQ GHUMMAN
ISLAMABAD (August 06 2009): The National Electric Power Regulatory Authority (Nepra) has authorised six discos to increase their power tariffs, ranging from 26 paisa to 49 paisa per unit, but refused to annex mark-up with the tariff on delayed payment to IPPs. Quetta Electric Supply Company (Qesco) and Gujranwala Electric Power Company (Gepco), however, have been asked to reduce their tariff by Rs 1.54 per unit and 0.02 paisa per unit respectively.

The regulator has given determinations for discos under the monthly tariff adjustment formula at a time when the whole nation is passing through 'hell' in the absence of electricity.

According to details, the Authority considered Fesco's request for monthly adjustment of power purchase price (PPP) variation for the month of April 2009 pursuant to paragraph II of the order of the Authority of August 23, 2008. According to the information/evidence placed before the Authority the actual PPP for the month of April 2009, charged to Fesco by Central Power Purchasing Agency (CPPA) was Rs 6.1915/kWh.

The Authority observed that in April 2009 CPPA charged a substantial amount of Rs 2.685 billion in energy charge and Rs 683 million in the capacity charge on account of previous month's adjustment. According to the information provided by CPPA the major component of this adjustment pertain to mark-up on delayed payment to IPPs which was Rs 2.495 billion in energy charge and Rs 413.24 million in capacity charge.

The Authority considers that the mark-up on delayed payment to IPPs is not covered under monthly power purchase price adjustment mechanism and needs to be considered separately. The Authority has, therefore, decided not to allow Rs 2.908 billion on account of mark-up on delayed payment to IPPs.

The Authority directed CPPA to revise the invoices for the month of April 2009 accordingly. After excluding the impact of mark-up on delayed payment, the actual PPP has been worked out Rs 5.7253/kWh, which was Rs 02757/kWh higher than the reference PPP of Rs 5.4496/kWh.

After incorporating the impact of target distribution losses of 11.23 percent, the required upward per unit adjustment in the determined tariff has been assessed as Rs 0.32. This adjustment shall apply to all consumer categories except lifeline residential consumers.

In case of Gepco, the Authority observed that in April 2009 CPPA charged a substantial amount of Rs 2.685 billion in energy charge and Rs 683 million in the capacity charge on account of previous months' adjustment. According to the information provided by CPPA, the major component of this adjustment pertain to mark-up on delayed payment to IPPs which was Rs 2.495 billion in energy charge and Rs 413.24 million in capacity charge.

The Authority considers that the mark-up on delayed payment to IPPs is not covered under monthly power purchase price adjustment mechanism and needs to be considered separately. The Authority has, therefore, decided not to allow Rs 2.908 billion on account of mark-up on delayed payment to IPPs. After excluding the impact of mark-up on delayed payment, the actual PPP has been worked out Rs 5.7831/kWh, which is Rs 0.0139/kWh lower than the reference PPP of Rs 5.7970/kWh.

After incorporating the impact of target distribution losses of 11.25 percent the required downward per unit adjustment in the determined tariff has been assessed as Rs 0.02. This adjustment will apply to all consumer categories except lifeline residential and agricultural consumers.

While considering the petition of Hesco, the Authority observed that in April 2009 CPPA charged a substantial amount of Rs 2.685 billion in energy charge and Rs 683 million in the capacity charge on account of previous months' adjustment. According to the information provided by CPPA, the major component of this adjustment pertain to mark-up on delayed payment to IPPs which was Rs 2.495 billion in energy charge and Rs 413.24 million in capacity charge.

The Authority considers that the mark-up on delayed payment to IPPs is not covered under monthly power purchase price adjustment mechanism and needs to be considered separately. The Authority has, therefore, decided not to allow Rs 2.908 billion on account of mark-up on delayed payment to IPPs.

After excluding the impact of mark-up on delayed payment, the actual PPP has been worked out Rs 5.6852/kWh, which is Rs 0.2438/kWh higher than the reference PPP of Rs 5.4414/kWh. After incorporating the impact of target distribution losses of 34 percent, the required upward per unit adjustment in the determined tariff has been assessed as Rs 0.38.

This adjustment shall apply to all consumer categories except lifeline residential consumers. In case of Iesco, according to information/evidence placed before the Authority, the actual PPP for the month of April 2009, charged to Iesco by CPPA was Rs 6.1705/kWh. The authority observed that in April 2009 CPPA charged a substantial amount of Rs 2.685 billion in energy charge and Rs 683 million in the capacity charge on account of previous months' adjustment.

According to the information provided by CPPA, the major component of this adjustment pertains to was Rs 2.495 billion in energy charge and Rs 413.24 million in capacity charge. The Authority considers that the mark-up on delayed payment to IPPs is not covered under monthly power purchase price adjustment mechanism and needs to be considered separately.

The Authority has, therefore, decided not to allow Rs 2.908 billion on account of mark-up on delayed payment to IPPs. After excluding the impact of mark-up on delayed payment, the actual PPP has been worked out Rs 5.7051/kWh, which is Rs 0.2565/kWh higher than the reference PPP of Rs 5.4486/kWh.

After incorporating the impact of target distribution losses of 11 percent, the required upward per unit adjustment in the determined tariff has been assessed as Rs 029. This adjustment shall apply to all consumer categories except lifeline residential consumers.

LESCO: The Authority after excluding the impact of mark-up on delayed payment, said the actual PPP has been worked out Rs 5.6274/kWh, which is Rs 0.2274/kWh higher than the reference PPP of Rs 5.4000/kWh. After incorporating the impact of target distribution losses of 12.30 percent, the required upward per unit adjustment in the determined tariff has been assessed as Rs 0.26. The adjustment shall apply to all consumer categories except lifeline residential consumers.

MESCO: The Authority after excluding the impact of mark-up on delayed payment, said the actual PPP has been worked out Rs 5.5803/kWh, which is Rs 0.2170/kWh higher than the reference PPP of Rs 5.3633/kWh. After incorporating the impact of target distribution losses of 17.50 percent, the required upward per unit adjustment in the determined tariff has been assessed as Rs 0.27. The adjustment shall apply to all consumer categories except lifeline residential consumers.

PESCO: The Authority after excluding the impact of mark-up on delayed payment, said the actual PPP has been worked out Rs 5.6691/kWh, which is Rs 0.3081/kWh higher than the reference PPP of Rs 5.3610/kWh. After incorporating the impact of target distribution losses of 33.20 percent, the required upward per unit adjustment in the determined tariff has been assessed as Rs 0.49. The adjustment shall apply to all consumer categories except lifeline residential consumers.

QESCO: The Authority after excluding the impact of mark-up on delayed payment, said the actual PPP has been worked out Rs 5.2962/kWh, which is Rs 0.3142/kWh higher than the reference PPP of Rs 5.6104/kWh. After incorporating the impact of target distribution losses of 20.50 percent, the required upward per unit adjustment in the determined tariff has been assessed as Rs 1.54. The adjustment shall apply to all consumer categories except lifeline residential consumers.

http://www.brecorder.com/index.php?id=94...=&supDate=
Quote this message in a reply
Post Reply 


Possibly Related Threads...
Thread: Author Replies: Views: Last Post
  Nepra fails to resolve ‘overcharging’ dispute LRE-Azan 0 654 01-26-2023 02:34 PM
Last Post: LRE-Azan
  Information technology to raise living standard: CM Salman 0 4,743 02-24-2012 12:30 PM
Last Post: Salman
  Film festival held to raise awareness about violence against women Lahore_Real_Estate 0 4,136 03-04-2011 05:12 PM
Last Post: Lahore_Real_Estate
  Govt will try to raise POL prices on 31st Lahore_Real_Estate 0 3,228 01-29-2011 02:18 PM
Last Post: Lahore_Real_Estate
  DHA elections raise residents’ hopes of participatory decision-making Lahore_Real_Estate 0 3,649 12-04-2010 12:08 PM
Last Post: Lahore_Real_Estate
  GST will raise poultry prices by 40pc Lahore_Real_Estate 0 3,421 11-16-2010 01:49 PM
Last Post: Lahore_Real_Estate
  Pakistan aims to raise Rs 80b from Islamic bond Lahore_Real_Estate 0 3,505 10-30-2010 04:25 PM
Last Post: Lahore_Real_Estate
  Qureshi urges Obama to raise Kashmir issue with India Lahore_Real_Estate 0 4,036 10-23-2010 12:30 PM
Last Post: Lahore_Real_Estate
  NEPRA raises power tariff by 64 paisas per unit Lahore_Real_Estate 0 3,859 07-27-2010 01:14 PM
Last Post: Lahore_Real_Estate
  Government employees, pensioners get raise Lahore_Real_Estate 0 5,504 07-07-2010 12:36 PM
Last Post: Lahore_Real_Estate
  FBR to find other sources to raise Rs 30bn if GST not increased Lahore_Real_Estate 0 3,603 06-12-2010 11:43 AM
Last Post: Lahore_Real_Estate
  Punjab govt set to announce 50% pay raise for govt employees Lahore_Real_Estate 0 4,699 06-12-2010 11:42 AM
Last Post: Lahore_Real_Estate
  800pc raise in LDA commercialisation fee Lahore_Real_Estate 0 3,425 01-26-2010 01:18 PM
Last Post: Lahore_Real_Estate
  Govt to raise power tariff by 13.6% Jan, another 6% by April: Tarin Naveed Yaseen 0 3,338 11-16-2009 09:16 PM
Last Post: Naveed Yaseen
  Pakistan to raise power, gas tariffs another 12% on IMF demand Naveed Yaseen 0 4,289 11-14-2009 06:38 AM
Last Post: Naveed Yaseen
  Raise tariff to end loadshedding: US Naveed Yaseen 0 3,757 11-06-2009 06:04 AM
Last Post: Naveed Yaseen
  Govt considering another 15% raise in power prices Naveed Yaseen 0 2,863 10-08-2009 08:27 AM
Last Post: Naveed Yaseen
  Seven percent raise in power tariff likely from October 1 Naveed Yaseen 0 3,132 09-27-2009 05:21 AM
Last Post: Naveed Yaseen
  Nepra refuses to approve tariff of 3 IPPs selected in Intl Competitive Bidding Naveed Yaseen 0 3,299 09-12-2009 05:46 AM
Last Post: Naveed Yaseen
  Thar Coal Power Project: Sindh, Engro sign agreement for power generation LahoreEstate 0 6,459 09-09-2009 06:37 AM
Last Post: LahoreEstate

Forum Jump:


User(s) browsing this thread: 1 Guest(s)