Mangla repairs to take two months, at least

By Umer Bhatti
LAHORE: The Monday’s short-circuiting of 10 turbines at the Mangla Hydro Power Station will take at least two months for repair, The News has learnt.

The entire power plant came to a grinding halt after the mishap, which, the sources revealed, was the result of Mangla managers’ attempt to push the worn-out system beyond limits, taking the total generation to 1,150 MW against the normal 1,000 MW. The original ‘oil-filled’ cables, having outlived their utility, could not survive the extra load, leading to the disaster. The Wapda had already awarded the tender for the replacement of these underground oil-filled cables. These cables, joining the turbines with the national grid, had a lifespan of 30 years and should have been replaced till 1997.

The sources said initially the cables of two turbines heated up due to overloading, leading to spark in one of the turbines, which turned into a full-blown fire. The sources also said that the Wapda authorities were repeatedly informed by the officials of the Mangla Dam project to replace these cables to avoid any future setback, but the hierarchy gave a deaf ear to these requests.

The issue of replacing the oil-filled cables, the sources revealed, was taken up some two years ago, and finally the Wapda considered two companies — M/s SGWI and Excel Technological Services (ETS) — to award the contract in February 2008. The contract was finally awarded to ETS in February 2009. Ironically, the work on the project was yet to begin.

The total length of the tunnel, having all the cables, is one kilometre. Managing Director Pepco Tahir Basharat Cheema has said “we are going to lay the overhead cable, which would hasten the recovery process and save time”. But experts say it would take around 3-4 months even if the cables were installed overhead. It was also learnt there was no local expertise available in the country so the expertise had to be called from abroad.

Sources in the Wapda claimed the authority did not have the power cable in hand and planning to import it from Saudi Arabia. According to a former member Wapda, if the cables in any of the turbine in a power station get overloaded, there exist certain instruments called ‘Protection Relays’, which should be operated right after an emergency occurs. He said these relays were battery-operated and it is possible that the batteries were not charged or the ‘Protection Relays’ were out of work altogether. The News made a number of calls to get the version of Wapda Chairman Shakil Durrani and other officials but no one attended the calls. The story of CD’s evaluation of foreign gifts

http://www.thenews.com.pk/top_story_detail.asp?Id=23032

07-01-2009 05:18 AM
Find all posts by this user Quote this message in a reply
Post Reply  Post Thread 

Possibly Related Threads...
Thread: Author Replies: Views: Last Post
  300 new industrial units to be set up in 15 months Lahore_Real_Estate 0 38 09-02-2010 03:00 PM
Last Post: Lahore_Real_Estate
  Pak Parlimentarians: PHD in 2 Months...! Assad 0 192 05-28-2010 01:05 AM
Last Post: Assad
  SC directs Rangers to vacate building in two months Lahore_Real_Estate 0 146 04-23-2010 10:46 AM
Last Post: Lahore_Real_Estate
  And Now Education: Teachers to be Appointed for 6 Months Only! Assad 0 119 04-09-2010 01:42 AM
Last Post: Assad
  Gwdar Port: Rs 120 Million Loss in 8 Months Assad 0 176 03-27-2010 11:33 PM
Last Post: Assad
  Remittances rise by 21% in first 7 months of FY10 Hamid 0 169 02-11-2010 07:43 AM
Last Post: Hamid
  List of 20 PPP Govt blunders in the last 20 months by Hamid Mir Hamid 0 395 11-28-2009 05:33 AM
Last Post: Hamid
  Auto sales expected to improve in few months Naveed Yaseen 0 189 11-22-2009 06:24 AM
Last Post: Naveed Yaseen
  National grid to get 2,500MW in three months: Raja Hamid 0 168 11-08-2009 05:35 AM
Last Post: Hamid
  Karachi being supplied untreated water for 1.5 months Naveed Yaseen 0 162 10-09-2009 06:08 AM
Last Post: Naveed Yaseen
  First public offering after 10 months Hamid 0 269 09-05-2009 08:05 AM
Last Post: Hamid
  Punjab wants Mangla, Ghazi Barotha royalty Naveed Yaseen 0 183 08-29-2009 07:15 AM
Last Post: Naveed Yaseen
  ‘Mangla power house fault fixed’ Hamid 0 113 07-11-2009 07:17 AM
Last Post: Hamid
  PM orders no power tariff raise for next six months Naveed Yaseen 0 153 06-25-2009 07:29 AM
Last Post: Naveed Yaseen
  Remittances rise to $7.076 billion in 11 months Hamid 0 154 06-12-2009 08:34 AM
Last Post: Hamid
  Peshawar: Hashwani vows to rebuild PC in two months Naveed Yaseen 0 139 06-11-2009 08:06 AM
Last Post: Naveed Yaseen
  LSM growth negative for 10 months in a row Hamid 0 151 06-05-2009 07:31 AM
Last Post: Hamid
  Pakistan's budget deficit for nine months at 3.0 percent of GDP Hamid 0 106 05-31-2009 05:56 AM
Last Post: Hamid
  Ministry wants to ban new cars tranfer within 6 months of purchase Naveed Yaseen 0 156 05-28-2009 07:59 AM
Last Post: Naveed Yaseen
  Punjab uses 45.89pc ADP funds in 9 months Naveed Yaseen 0 167 05-19-2009 06:37 AM
Last Post: Naveed Yaseen

View a Printable Version
Send this Thread to a Friend
Subscribe to this Thread | Add Thread to Favorites
Rate This Thread:

Forum Jump: