SHC seeks reply from DHA
10-21-2014, 03:14 PM
Post: #1
SHC seeks reply from DHA
The Sindh High Court (SHC) on Monday sought comments from the Defence Housing Authority (DHA) and other provincial authorities on an application of real estate concern seeking resumption of construction work on a flyover and two underpasses in Clifton area.

The counsel for Bahria Town filed an application requesting court to allow it to resume construction work on the traffic improvement project as Sepa has given an EIA report on the project.

He submitted that following the court directives, the KMC approached the Sepa to obtain a mandatory environmental impact assessment (EIA) report on the project. He added that since the Sepa had accorded its approval to the project on August 5, the builder be allowed to start work on the project.

He told the judge that SHC’s division bench had also dismissed the DHA’s petition through which it challenged Sepa’s EIA report. Hence, he pleaded the court to allow Bahria Town to resume work on the project.

After the preliminary hearing, the single bench headed by Justice Muneeb Akhtar issued notice to relevant authorities to file comments on application by October 22.
Visit this user's website Find all posts by this user
Quote this message in a reply
Post Reply 


Possibly Related Threads...
Thread: Author Replies: Views: Last Post
  SHC seeks NESPAK report on AKD venture Salman 0 2,416 03-14-2015 02:55 PM
Last Post: Salman
  SHC seeks reply from real estate firm, others in Clifton project case Salman 0 2,648 12-09-2014 01:41 PM
Last Post: Salman
  LHC Seeks Reply on Illegal Multi-Storey Buildings Salman 0 2,475 10-24-2014 01:36 PM
Last Post: Salman

Forum Jump:


User(s) browsing this thread: 1 Guest(s)