Post Reply 
 
Thread Rating:
  • 0 Vote(s) - 0 Average
  • 1
  • 2
  • 3
  • 4
  • 5
Mareer Railway Bridge Project misses another deadline
05-03-2014, 03:41 PM
Post: #1
Mareer Railway Bridge Project misses another deadline
Mareer Railway Bridge Project misses another deadline

Rawalpindi

The Rawalpindi Development Authority, which had made tall claims of completing the second phase of Mareer Railway Bridge Project by April 30 has missed the deadline and given a new date for finishing the project.

RDA Deputy Director Umar Farooq told this scribe that almost the work on the project is completed and now task of rivets fixing has to be completed, which would be over by 10th of May.

After completing rivets work, the remaining process of the project would be handed over to Pakistan Railways for laying down tracks.

To a question that how much time, tracks work is likely to be completed by the Pakistan Railways, he said it depends upon them as how much time they want to finish it.

The work on first component of Railway bridge was initiated in September, 2012 and was to be completed by the end of fiscal year 2013. However, due to funds problem, it remained suspended for many times, resulting in delay in completion of the project. The work on first component expansion and widening of railway bridge was finally completed in November, 2013.

Work on second component commenced in December 2013, which was done on fast note without any suspension. The total cost of the project was estimated at Rs500 million, which were released in phases.

According to Railway Officials, work on tracks laying does not take much time and is carried out in three to four days. The operation of trains on new railway bridge is likely to begin from June 15
Visit this user's website Find all posts by this user
Quote this message in a reply
Post Reply 


Possibly Related Threads...
Thread: Author Replies: Views: Last Post
  LDA City Lahore Development Progress: Chenab Road Bridge | C Block Possession Updates LRE-Azan 0 227 11-22-2023 07:15 PM
Last Post: LRE-Azan
  Lahore Smart City Development of the Railway Line Underpass Started Good News LRE-Azan 0 531 01-24-2023 02:53 PM
Last Post: LRE-Azan
  LDA City Lahore Extends Deadline To Pay Development Charges LRE-Azan 0 1,734 04-22-2020 08:34 PM
Last Post: LRE-Azan
  DHA Bahawalpur Main Entrance Bridge Near Completion Latest Update by LRE Dec 2018 LRE-Azan 0 2,004 12-13-2018 09:06 PM
Last Post: LRE-Azan
  Federal Minister - Pakistan Railway New modern Railway Station to establish in Gwadar LRE-Azan 0 1,935 11-15-2018 06:18 PM
Last Post: LRE-Azan
  DHA Gujranwala 5 Marla Plots – 1st Installment Payment Deadline & Instruction LRE-Azan 0 2,698 07-02-2018 06:12 PM
Last Post: LRE-Azan
  CPEC railway line economic zone projects face delay Salman 0 2,259 09-22-2017 06:21 PM
Last Post: Salman
  Orange Line Metro Project (Arch Bridge) Salman 0 2,925 09-06-2016 04:05 PM
Last Post: Salman
  Raiwind Road railway track flyover foundation stone laid Salman 0 3,139 08-23-2016 12:50 PM
Last Post: Salman
  Raiwind Road railway track flyover foundation stone laid Salman 0 2,879 08-23-2016 11:56 AM
Last Post: Salman
  Construction of Underpass at Railway crossing near Gurumangat road,Lahore Salman 0 3,798 08-11-2016 12:40 PM
Last Post: Salman
  Flyover over railway line at Peco Mor, Kacha Jail road to be constructed soon! Salman 0 5,544 05-17-2016 06:38 PM
Last Post: Salman
  Construstion Of Underpass At Railway Crossing Near Gurumangat Road lahore Salman 0 4,021 05-14-2016 12:26 PM
Last Post: Salman
  CDA gives 10-day deadline to owners Salman 0 2,522 09-21-2015 03:11 PM
Last Post: Salman
  Metro misses third deadline Salman 0 2,185 02-16-2015 05:52 PM
Last Post: Salman
  District Govt Gives New Deadline For Computerisation Of Land Records Salman 0 2,649 02-03-2015 05:37 PM
Last Post: Salman
  Bahria Heights project will be completed before deadline: Ali Riaz Salman 0 2,464 11-29-2014 01:23 PM
Last Post: Salman
  Metro bus contractors of phase-I & III directed to meet Dec 25 deadline Salman 0 2,580 11-24-2014 12:47 PM
Last Post: Salman
  Influential People Occupied Acres of Railway Land Salman 0 2,556 10-10-2014 12:49 PM
Last Post: Salman
  Deadline of Metro Bus Project extended Salman 0 2,422 09-25-2014 02:15 PM
Last Post: Salman

Forum Jump:


User(s) browsing this thread: 1 Guest(s)