Lowari Tunnel – Construction Work Expected To Complete In Three Years
10-23-2013, 12:23 PM (This post was last modified: 10-23-2013 12:26 PM by Salman.)
Post: #1
Lowari Tunnel – Construction Work Expected To Complete In Three Years
Islamabad – The construction work on Lowari Tunnel project is in progress. It is expected that the work will be completed in three years.

The work on Lowari Tunnel Project was commenced in September 2005 and by January 2009, excavation of 8150 metres tunnel was completed. Owing to the conversion of project from rail tunnel to road tunnel, additional excavation is being carried out to widen the tunnel.

This tunnel will provide an access to Central Asian Republics and Afghanistan and it will also facilitate tourism and trade. The provincial government of Khyber Pakhtunkhwa has decided to allocate Rs 3 billion for early completion of current projects, including the Lowari Tunnel project.
Visit this user's website Find all posts by this user
Quote this message in a reply
Post Reply 


Possibly Related Threads...
Thread: Author Replies: Views: Last Post
  DHA Bahawalpur Sector Z - Files Prices Overview | Expected Ballot & Future Prospects LRE-Azan 0 458 05-16-2023 07:37 PM
Last Post: LRE-Azan
  KP CM Direct to start construction work on Dir Motorway 30-kilometre long LRE-Azan 0 667 01-26-2023 02:59 PM
Last Post: LRE-Azan
  Land acquisition for motorway complete, says DCO Salman 0 5,591 04-21-2015 02:42 PM
Last Post: Salman
  CDA to complete Kashmir Highway project by May 31 Salman 0 4,409 02-25-2014 01:22 PM
Last Post: Salman
  Construction Of Mehran Hotel Flyover – Arrangements Complete Salman 0 6,658 12-02-2013 01:47 PM
Last Post: Salman
  Sindh : 293 development schemes to complete by Dec 31 Salman 0 6,460 11-25-2013 01:34 PM
Last Post: Salman
  Construction of Iqbal Town parking plaza complete Salman 0 6,495 11-25-2013 01:28 PM
Last Post: Salman
  SC takes suo motu notice of Margalla Hills Tunnel Project Salman 0 6,047 09-30-2013 03:44 PM
Last Post: Salman
  Road From LOS To Multan Road, Construction Work On The Go Salman 0 12,519 09-23-2013 03:18 PM
Last Post: Salman
  CDA needs Rs3.6 billion to complete remaining part Salman 0 4,776 07-02-2013 12:43 PM
Last Post: Salman
  CDA directs to expedite Margalla construction work Salman 0 5,111 05-30-2013 06:37 PM
Last Post: Salman
  CDA fails to complete uplift work in D-12 Salman 0 5,654 05-15-2013 04:45 PM
Last Post: Salman
  CDA to expedite construction work on Margalla Avenue Salman 0 5,307 04-29-2013 01:46 PM
Last Post: Salman
  CDA to expedite construction work on Margalla Avenue Salman 0 5,311 04-24-2013 01:15 PM
Last Post: Salman
  Mareer Tunnel project to be completed in time Salman 0 5,145 03-11-2013 07:51 PM
Last Post: Salman
  Mareer Chowk tunnel project to be completed by March 15 Salman 0 5,089 01-10-2013 01:25 PM
Last Post: Salman
  Amended design of Mareer Chowk Railway Tunnel still awaits approval Salman 0 5,591 11-30-2012 02:14 PM
Last Post: Salman
  Work on Mureer Tunnel to start by month-end Salman 0 4,811 11-19-2012 12:15 PM
Last Post: Salman
  Marrer Tunnel construction to start soon Salman 0 4,330 11-12-2012 12:41 PM
Last Post: Salman
  Work remains incomplete in I-14 sector even after 15 years Salman 0 3,759 11-02-2012 04:35 PM
Last Post: Salman

Forum Jump:


User(s) browsing this thread: 1 Guest(s)