CDA fails to complete final loop of Zero Point interchange

Cash-strapped civic body has given several deadlines - Despite lapse of several deadlines, the cash-strapped Capital Development Authority (CDA) is still finding it hard to complete the under-construction loop at Zero Point interchange which will provide passage to the traffic coming from Faisal Mosque to reach Kashmir Highway or across Islamabad Highway. The said loop will also provide an easy way to the visitors of National Monument to reach their destination without any inconvenience. Currently, those intending to visit the monument have to face many troubles due to the unavailability of any proper way.
Sources in the CDA told Pakistan Today that the authority had not enough funds to complete the construction work within the due time, adding it had decided to complete the work in October 2011, but some senior officials of the civic body had paid their attention towards the other costly projects and ignored the completion of the loop, a part of Zero Point interchange project which had been inaugurated by Prime Minister Yousuf Raza Gilani a couple of months ago. They said National Monument was also said to be one of the main hurdles to the construction of the loop, adding it had also led to changes in the design of the interchange and reduction in the size of the loop.
“Every week, I visit the monument, but the only thing which irks me and other visitors as well is that no easy access has been provided by the CDA to reach the monument,” said Fahad Amjad, a visitor. He added that public transport was also not available to reach the monument, adding transporters had their route from Kashmir Highway and if the authority completed the loop, it would also become easy for the people to reach the recreational spot by using public transport.
The sources are of the view that the completion of the construction work on the loop is only possible if the CDA bosses pay heed towards it.
The interchange was scheduled to be completed by September 31, 2010, but the contractor argued that nonpayment of his dues, VVIP movement on Islamabad Highway and hurdles to the construction work due to the monument had caused the delay. “Though the interchange was formally inaugurated by Prime Minister Yousuf Raza Gilnai in July, the process of compaction and reinforcement of hillock has already taken a couple of months,” he said.

02-20-2012 01:27 PM
Find all posts by this user Quote this message in a reply
Post Reply  Post Thread 

Possibly Related Threads...
Thread: Author Replies: Views: Last Post
  CDA fails to complete uplift work in D-12 LRE - Salman 0 302 05-15-2013 04:45 PM
Last Post: LRE - Salman
  Flawed Interchange design to cost CDA Rs700 million LRE - Salman 0 309 12-28-2012 03:46 PM
Last Post: LRE - Salman
  CDA fails to execute parking plaza plan in capital LRE - Salman 0 311 12-26-2012 12:23 PM
Last Post: LRE - Salman
  RDA fails to recover Rs5.9m after lapse of 17 years LRE - Salman 0 1,159 11-19-2012 12:16 PM
Last Post: LRE - Salman
  Bus project devours Ring Road south loop LRE - Salman 0 1,135 11-17-2012 01:36 PM
Last Post: LRE - Salman
  Lahore Ring Road News : Work on southern loop of Ring Road to start soon LRE - Salman 0 1,672 11-05-2012 12:05 PM
Last Post: LRE - Salman
  CDA fails to get land for Magalla Avenue extension LRE - Salman 0 1,004 10-08-2012 12:21 PM
Last Post: LRE - Salman
  CDA fails to develop Park Enclave LRE - Salman 0 1,391 09-06-2012 03:22 PM
Last Post: LRE - Salman
  TMA fails to get dangerous buildings vacated LRE - Salman 0 681 07-23-2012 12:33 PM
Last Post: LRE - Salman
  CM invites Turk help for southern loop of Ring Road LRE - Salman 0 638 05-26-2012 12:26 PM
Last Post: LRE - Salman
  Financial crunch delays Zero Point loop construction LRE - Salman 0 623 04-25-2012 12:42 PM
Last Post: LRE - Salman
  CDA fails to start development work LRE - Salman 0 846 04-24-2012 01:06 PM
Last Post: LRE - Salman
  PHA asked to complete service roads till May 10 LRE - Salman 0 989 04-19-2012 01:00 PM
Last Post: LRE - Salman
  New toll plaza at Ravi Interchange irks citizens LRE - Salman 0 717 03-22-2012 02:57 PM
Last Post: LRE - Salman
  CDA fails to evacuate illegal Kacchi Abadeis LRE - Salman 0 612 03-17-2012 02:17 PM
Last Post: LRE - Salman
  Private housing schemes LDA directorate to complete development work LRE - Salman 0 498 03-06-2012 06:34 PM
Last Post: LRE - Salman
  Pak, Iran agree to complete power import projects soon LRE - Salman 0 550 02-15-2012 01:16 PM
Last Post: LRE - Salman
  CDA fails to maintain main roads in Islamabad LRE - Salman 0 704 01-31-2012 01:25 PM
Last Post: LRE - Salman
  Residential plots auction fails to fetch good price LRE - Salman 0 1,058 01-11-2012 11:54 AM
Last Post: LRE - Salman
  CDA fails to retrieve land from illegal occupants LRE - Salman 0 672 01-06-2012 01:33 PM
Last Post: LRE - Salman

View a Printable Version
Send this Thread to a Friend
Subscribe to this Thread | Add Thread to Favorites
Rate This Thread:

Forum Jump:

 

 Plots For Sale By Lahore Real Estate

 

Lahore Master Plan HTML

Lahore Master Plan Interactive Map