Canal road project to be completed in 1st week of Jan
12-30-2011, 12:17 PM
Post: #1
Canal road project to be completed in 1st week of Jan
Lahore—The widening of the canal road project will be completed in the first week of January 2012. More than 80 percent work has been completed on the site while Asphaltic Wearing Course work and carpeting would be finished till the said date which is rapidly in progress by National Logistics Cell (NLC) and Communication and Works Department Punjab.

It is pertinent to mention that the project took 25 days extra from the stipulated time frame given by the Chief Minister Shahbaz Sharif as the PC-1 of the project was revised to include additional works like the light pools of Light- Emitting Diode (LED), horticulture, foot paths, drainage, telephones and sui gas lines.

Muhammed Shahid-Resident officer of NESPAK,the consultant company of project, told here Thursday that initially government approved the PC-1 worth Rs 1016 millions and the revised plan would cost Rs 1513 millions adding that the Chief Minister approved the project.

Syed Nafasat Raza Zaidi,Executive Engineer Communication and Works department stated that under the project, approximately 17.2 kilometre total road from both sides would be widened from Mall road underpass to Doctors Hospital. Some portions in the said area already have been widened like FC college Under pass to New Campus bridge and these were not included in the project.

He added that the road having width of 42 feet on one side and 84 feet total of both sides would be comprised on three and half lanes along with shoulders and parking area. A special Bus lane would also be made for the heavy traffic and public service vehicles on the road.

Nafasat Zaidi,added that after the completion, Canal Road would facilitate tens of thousands of people daily besides easing the traffic mess which had been made routine every time on the road.
Visit this user's website Find all posts by this user
Quote this message in a reply
Post Reply 


Possibly Related Threads...
Thread: Author Replies: Views: Last Post
  CM Naqvi Drives Forward Controlled Access Corridor Band Road Project in Lahore LRE-Azan 0 128 01-24-2024 06:40 PM
Last Post: LRE-Azan
  Commissioner Announces Key Milestones and Schedule for Rawalpindi Ring Road Project LRE-Azan 0 126 01-23-2024 03:37 PM
Last Post: LRE-Azan
  Latest News Lahore-Sialkot Motorway Link Road Project Set to Open in January LRE-Azan 0 137 01-16-2024 02:26 PM
Last Post: LRE-Azan
  Lahore-Sialkot Motorway Link Road Project Set to Open in January LRE-Azan 0 134 01-16-2024 02:25 PM
Last Post: LRE-Azan
  Rawalpindi Ring Road (RRR) Project: 12% Completion, Anticipated Opening in August LRE-Azan 0 162 01-02-2024 06:14 PM
Last Post: LRE-Azan
  Signal-Free Walton Road Project: Tackling 18-Kilometer Infrastructure and Drainage Is LRE-Azan 0 189 12-11-2023 04:06 PM
Last Post: LRE-Azan
  Rawalpindi Ring Road Project Set to Be Completed in One Year LRE-Azan 0 292 10-11-2023 07:13 PM
Last Post: LRE-Azan
  Rawalpindi Ring Road Project Faces Complication of Missing Land Record LRE-Azan 0 298 09-13-2023 07:36 PM
Last Post: LRE-Azan
  DHA Multan to Host Housing & Construction Expo 2023 This Week LRE-Azan 0 284 09-11-2023 01:13 PM
Last Post: LRE-Azan
  Directive To Clear LDA Pending Records Within A Week LRE-Azan 0 543 04-11-2023 05:19 PM
Last Post: LRE-Azan
  Good news: Margalla Avenue to be Completed ‘Very Soon’ – Chairman CDA LRE-Azan 0 781 01-21-2023 01:15 PM
Last Post: LRE-Azan
  Lahore New: Saggian-Sharaqpur Road Project is inaugurated by CM Parvez Elahi LRE-Azan 0 704 01-21-2023 01:04 PM
Last Post: LRE-Azan
  HYDERABAD-SUKKUR MOTORWAY TO BE COMPLETED IN 2 YEARS LRE-Azan 0 618 01-18-2023 03:07 PM
Last Post: LRE-Azan
  Rawalpindi: Kachehri Chowk Signal Free project, Hearing of Objections Completed LRE-Azan 0 1,194 03-02-2022 06:54 PM
Last Post: LRE-Azan
  Faisalabad: Demolition of Illegal Commercial Market on Canal Expressway LRE-Azan 0 1,095 03-02-2022 06:50 PM
Last Post: LRE-Azan
  Rawal Dam Chowk Interchange likely to be completed by June 2022 LRE-Azan 0 1,420 12-15-2021 05:48 PM
Last Post: LRE-Azan
  Rawalpindi Ring Road Project New Design is Ready LRE-Azan 0 1,317 11-20-2021 12:22 PM
Last Post: LRE-Azan
  Rawalpindi: Ring Road Project, Rs. 24 Billion Approved in PC-1 LRE-Azan 0 1,156 10-27-2021 01:04 PM
Last Post: LRE-Azan
  LWMC has Launched an Operation to make Mall Road a Model road of the City LRE-Azan 0 4,133 08-09-2018 06:35 PM
Last Post: LRE-Azan
  Shahbaz Sharif reviews Ring Road project Salman 0 6,119 03-13-2014 05:18 PM
Last Post: Salman

Forum Jump:


User(s) browsing this thread: 1 Guest(s)