Another underpass along canal road planned

LAHORE:

The Lahore Development Authority (LDA) plans to construct an underpass near Royal Palm Golf and Country Club to improve the traffic flow.

The underpass is the last one along the canal in the northern part of the city.

Israr Saeed, the Traffic Engineering and Transport Planning Agency (TEPA) director, told The Express Tribune that construction of the underpass is likely to begin in July. He said that the chief minister wanted its construction to begin soon.

The underpass, called Chawbucha Underpass, will be 1.3 kilometres (km) long and have three lanes on each side. It will be built under the Chawbucha railway crossing. One of the railway lines here leads to India and the other is used for shunting purposes.

Saeed said that a feasibility report had already been completed by the National Engineering Services (NESPAK). The Chawbucha crossing is closed several times a day, causing huge traffic jams. Once the project is successfully completed, the LDA say, one will be able to drive from one end of the canal to another without a major hurdle. The cost of the project has been estimated at Rs1.7 billion. Out of this Rs0.4 billion will be used to acquire land and Rs1.3 billion for construction purposes. LDA will acquire the 40 kanals land for the underpass from the Pakistan Railways, the Irrigation Department, WAPDA and some residents along a shrine next to one of the railway crossings.

Besides the 40 kanals of land, the LDA will also require a 50-foot corridor along the 1.3 km road on one side to add width to the road. Presently, the road is about 30-40 feet wide. The other side of the road has sufficient width in green belts. An LDA official said that funds for the project will be generated by the LDA through commercialisation fees. However, the LDA has requested the chief minister to provide the funds initially. The chief minister’s response to the request is expected next week, he said.

Saeed said that negotiations with the departments for land acquisition have already started. He said the project is expected to be completed by next year.

Saeed said that after the project is completed, the only bottleneck left on the route will be Lal Pul near Mughalpura.

The LDA is planning to widen the road at the point to ease traffic flow, he added.

“The name of the underpass might be changed,” he said. Saeed hoped that work on the Canal Road widening project would also begin soon, once the Supreme Court cleared the way.

07-01-2011 01:54 PM
Find all posts by this user Quote this message in a reply
Post Reply  Post Thread 

Possibly Related Threads...
Thread: Author Replies: Views: Last Post
  1,000-acre housing project planned LRE - Salman 0 190 05-15-2013 04:42 PM
Last Post: LRE - Salman
  Pirwadhai underpass opened to traffic, but flyover still closed LRE - Salman 0 429 03-22-2013 08:40 PM
Last Post: LRE - Salman
  Caved in roads threaten China Chowk underpass LRE - Salman 0 229 02-25-2013 03:56 PM
Last Post: LRE - Salman
  Kalma Chowk Underpass inauguration on 26th LRE - Salman 0 224 02-21-2013 03:20 PM
Last Post: LRE - Salman
  CM opens Model Town underpass LRE - Salman 0 424 01-15-2013 12:45 PM
Last Post: LRE - Salman
  Underpass approved for Judicial Complex LRE - Salman 0 423 12-21-2012 01:52 PM
Last Post: LRE - Salman
  Uprising’ against canal road widening LRE - Salman 0 311 12-17-2012 11:49 AM
Last Post: LRE - Salman
  Judicial Complex underpass project approved LRE - Salman 0 787 12-04-2012 04:43 PM
Last Post: LRE - Salman
  CM lays foundation of Rs1.4 billion flyover,underpass at Peshawar Road LRE - Salman 0 834 12-03-2012 11:59 AM
Last Post: LRE - Salman
  Work on Kalma underpass in progress LRE - Salman 0 788 11-27-2012 03:33 PM
Last Post: LRE - Salman
  Mehran underpass: Shifting of utility lines ordered LRE - Salman 0 444 10-16-2012 12:24 PM
Last Post: LRE - Salman
  Work on Pir Wadhai Underpass delayed LRE - Salman 0 635 10-11-2012 11:51 AM
Last Post: LRE - Salman
  SC stops work on Canal Road widening project LRE - Salman 0 785 10-03-2012 05:51 PM
Last Post: LRE - Salman
  Mareer Chowk underpass detailed design has been completed LRE - Salman 0 1,327 09-25-2012 03:46 PM
Last Post: LRE - Salman
  Kachhi Canal: A project that could revolutionize Balochistan LRE - Salman 0 602 08-03-2012 12:43 PM
Last Post: LRE - Salman
  Ill-planned construction continues in Zone-IV despite new regulations LRE - Salman 0 423 07-16-2012 12:39 PM
Last Post: LRE - Salman
  CDA Has Planned To Connect 7th Avenue With BB Road LRE - Salman 0 1,027 07-04-2012 02:49 PM
Last Post: LRE - Salman
  LDA to widen road from Allama Iqbal Town to Multan Road LRE - Salman 0 1,817 05-29-2012 03:06 PM
Last Post: LRE - Salman
  Underpass at Chaklala railway track approved LRE - Salman 0 542 04-07-2012 12:36 PM
Last Post: LRE - Salman
  Underpass project hits snag LRE - Salman 0 385 04-02-2012 12:30 PM
Last Post: LRE - Salman

View a Printable Version
Send this Thread to a Friend
Subscribe to this Thread | Add Thread to Favorites
Rate This Thread:

Forum Jump:

 

 Plots For Sale By Lahore Real Estate

 

Lahore Master Plan HTML

Lahore Master Plan Interactive Map