CM seeks revised feasibility report on Leh Expressway
Author Message
Lahore_Real_Estate
Super Moderator
******


Posts: 2,738
Group: Super Moderators
Joined: Nov 2009
Status: Offline
Reputation: 0
Post: #1
CM seeks revised feasibility report on Leh Expressway

Road likely to be extended to High Court Building according to original plan

By Tahir Rashid

RAWALPINDI: The Punjab government has again showed interest in commencing the mega project of Nullah Leh Expressway, as Punjab Chief Minister Shahbaz Sharif has directed Rawalpindi Development Authority (RDA) to submit the revised feasibility report on the expressway from High Court Building to Katarian Bridge, till 7 June.

RDA Director General Makeen Shahbaz told Daily Times that they had started work on redefining the project, which was approved by previous government to construct the Expressway from Ammar Chowk to Katarian Bridge, but now the road has been extended to High Court Building. The cost of the project will be also increased as the building material price has also increased manifold.

He said that construction of road on both banks of Nullah Leh from High Court building to Katarian Bridge was as per the actual master plan, conceived by the government when Shahbaz Sharif was the chief minister. The Punjab government wants to revive the original plan of the project, he said. “But presently the Punjab government has not enough funds to start the work on project immediately as closing of financial year is very near,” he said, adding, however it is very much possible that some amount may be allocated in next fiscal budget for the mega project.

It is pertinent to mention here that when ex-president Pervez Musharraf came into power, the Leh Expressway project, like many other development projects in the country, was shelved. But after sometime the former federal minister Sheikh Rashid tried to revive it, but this time it was decided to construct the expressway from Ammar Chowk to Katarian Bridge, reducing its total length. Musharraf inaugurated the Expressway project and announced to name it after Shiekh Rashid.

After general elections, Pakistan Muslim League-Nawaz (PML-N) soon after coming into power in the Punjab announced to abolish the project and start another project, the Elevated Expressway to be built over Benazir Bhutto Shaheed Road (Murree Road) from Flashman’s Hotel to Faizabad. The Punjab CM also inaugurated the project. Well-placed sources said the security reasons did not allow work on the project, which was abandoned in the planning phase.

The Punjab government has once again focused on the Leh Expressway as the PML-N legislators have asked the Punjab CM to review the project. As the result, RDA DG was asked to submit the revised plan.

05-29-2010 10:44 AM
Find all posts by this user Quote this message in a reply
Post Reply  Post Thread 

Possibly Related Threads...
Thread: Author Replies: Views: Last Post
  Punjab govt approves 21 revised development schemes LRE - Salman 0 297 05-13-2013 02:00 PM
Last Post: LRE - Salman
  Revised PC-I of Mareer Chowk Project Approved LRE - Salman 0 179 04-25-2013 04:08 PM
Last Post: LRE - Salman
  Pedestrians may soon find a wall on Expressway LRE - Salman 0 513 03-14-2013 05:41 PM
Last Post: LRE - Salman
  Shahbaz orders fresh feasibility study on Nullah Leh Expressway LRE - Salman 0 366 02-26-2013 11:39 AM
Last Post: LRE - Salman
  Residents For Head-Bridge Over Expressway LRE - Salman 0 191 02-02-2013 01:49 PM
Last Post: LRE - Salman
  Dawn.com Newspaper Lyari Expressway SHC stays demolition of houses in Liaq LRE - Salman 0 668 01-10-2013 01:29 PM
Last Post: LRE - Salman
  Expressway-II Project gets attention of city bosses LRE - Salman 0 226 12-12-2012 01:58 PM
Last Post: LRE - Salman
  Study on Feasibility of the Extension Metro Bus Service to Multan, GT roads LRE - Salman 0 1,269 11-05-2012 12:00 PM
Last Post: LRE - Salman
  President wants expressway to Zulfikarabad built LRE - Salman 0 631 11-02-2012 04:34 PM
Last Post: LRE - Salman
  Expediting work on Lyari Expressway directed LRE - Salman 0 547 10-10-2012 11:39 AM
Last Post: LRE - Salman
  Stalled project: Leh Expressway shelved, again LRE - Salman 0 853 09-17-2012 01:08 PM
Last Post: LRE - Salman
  Early completion of Lyari expressway demanded LRE - Salman 0 1,078 08-27-2012 06:09 PM
Last Post: LRE - Salman
  RDA seeks report on illegal constructions in three day LRE - Salman 0 645 08-02-2012 03:19 PM
Last Post: LRE - Salman
  RDA seeks report on illegal constructions in three days LRE - Salman 0 426 07-21-2012 03:57 PM
Last Post: LRE - Salman
  PML-N wants to re-launch Leh expressway project LRE - Salman 0 533 07-11-2012 05:01 PM
Last Post: LRE - Salman
  Lahore Development News : LDA approves revised estimate to improve traffic condition LRE - Salman 0 1,351 06-11-2012 01:22 PM
Last Post: LRE - Salman
  Lyari Expressway: ‘Remaining portion to be completed’ LRE - Salman 0 643 04-09-2012 01:27 PM
Last Post: LRE - Salman
  Feasibility report of parking area at Liaquat Road LRE - Salman 0 485 04-05-2012 03:16 PM
Last Post: LRE - Salman
  Malir River Expressway? In your dreams! LRE - Salman 0 711 01-19-2012 05:29 PM
Last Post: LRE - Salman
  Malir Expressway Project: Abbas orders expediting work LRE - Salman 0 473 01-16-2012 11:56 AM
Last Post: LRE - Salman

View a Printable Version
Send this Thread to a Friend
Subscribe to this Thread | Add Thread to Favorites
Rate This Thread:

Forum Jump:

 

 Plots For Sale By Lahore Real Estate

 

Lahore Master Plan HTML

Lahore Master Plan Interactive Map